  • DO YOU KNOW? It Is Illegal For Ikeja Electric, AEDC to Disconnect Customers’ Power Without Prior Notice

    DO YOU KNOW? It Is Illegal For Ikeja Electric, AEDC to Disconnect Customers’ Power Without Prior Notice

     

    A serving distribution company (DisCo) is obliged by the law to notify its customers in writing prior to the disconnection of electricity service in Nigeria. Surprised, right?

     

    This is according to the Nigerian Electricity Regulatory Commission (NERC) regulation on Connection and Disconnection Procedures for Electricity Service (CDPES).

     

    The NERC, empowered by the Electric Power Sector Reform (EPSR) Act, 2005,  has an obligation to ensure that the electricity supply industry is efficiently run to satisfy electricity needs of Nigerians.

     

    According to the EPSR Act, NERC is vested with the power to ‘establish appropriate consumers rights and obligations regarding the provision and use of electricity services amongst others.

     

    WHEN A DISCO CAN DISCONNECT CUSTOMERS’ ELECTRICITY SUPPLY

     

    According to the CDPES regulation, a DisCo can disconnect supply when the customer refuses to pay the amount correctly billed, at the payment date.

    DO YOU KNOW? It Is Illegal For Ikeja Electric, AEDC to Disconnect Customers’ Power Without Prior Notice

    This is dependent on the following factors:

     

    The payment date must be clearly indicated on the bill for a DisCo to be eligible to disconnect its customer’s power supply.

     

    The bill must have been delivered 10 working days before the payment deadline.

     

    A DisCo must ensure that the payment date has not been superseded by a subsequent payment date issued to the same customer.

    That’s not all.

     

    The distribution company must have checked its records to be sure that the bill had not been paid.

     

    Also, the regulation stated that electricity supply could be disconnected if the customer refuses to provide acceptable identification or security deposit, after the DisCo’s prior written notice.

     

    HOW SHOULD A WARNING BE ISSUED BY A DISCO?

     

    It is unlawful for a DisCo to barge into a customer’s premises to disconnect electricity without first writing to the supply address, even though the customer had outstanding bills before the disconnection date.

     

    The regulation said that before disconnection, the DisCo must have issued a written warning, stating specifically that the customer’s electricity supply will be disconnected, if the payment is not remitted at the appropriate date.

     

    The written warning must contain the date it was delivered to the customer’s address and a telephone number or address where the customer could call for assistance to pay the outstanding bill.

     

    WHEN CAN A DISCO DISCONNECT CUSTOMERS’ ELECTRICITY SUPPLY WITHOUT NOTICE?

     

    The provision stated that a customer’s electricity supply can be disconnected without notice only on three grounds.

     

    When a customer is illegally connected to the DisCo’s network, the company could disconnect the power supply without notice.

     

    Also, when the customers’ installation is deemed to be dangerous to the DisCo’s network, the quality of supply to other customers, it would be justifiable to cut off the electricity supply of such customers.

     

    WHAT A DISCO SHOULD DO WHEN A CUSTOMER’S METER CANNOT BE ACCESSED

     

    According to NERC’s provision, due to omission by the customer, a meter in the premises of a customer cannot be read for three consecutive times, the serving DisCo could disconnect power supply.

     

     

    The regulation stated further that this could be done only after the customer has been informed of the meter inaccessibility by written notice or telephone contact. This notification must include a request for the client to provide an access arrangement.

     

    Furthermore, the provision said that the DisCo should proceed to issue a warning notice to the customer, stating that unless access is granted, in not less than 10 working days, electricity will be disconnected.

     

    WHAT HAPPENS WHEN A CUSTOMER’S ELECTRICITY SUPPLY IS DISCONNECTED

     

    The Act noted that the DisCo has an obligation to notify its customer in writing — stating the date, time and reason for the disconnection. Also, the DisCo should inform its client about steps to take for reconnection.

     

    FINE FOR WRONGFUL DISCONNECTION

     

    The Act stated that if a DisCo wrongfully disconnects its customer’s power supply, it would have to pay a penalty fee every day or part of a day for the period of wrongful disconnection.

     

    The DisCo would be mandated to pay a daily fee of N1,000 for residential buildings, N1,500 for commercial buildings and N2000 for industrial and special customer classifications.

     

    The cable

  • It’s 8-Week Outage, Not Blackout, Says Ikeja Electric

    It’s 8-Week Outage, Not Blackout, Says Ikeja Electric

     

    Ikeja Electric Plc has said its customers need not to panic as the upgrade of the 132kv lines embarked upon by the Transmission Company of Nigeria, TCN would not result into total blackout as the power outage would only be between 8am and 6pm for the eight-week period.  

     

    Head of Corporate Communications, Ikeja Electric, Felix Ofulue, while making the clarification, told Business Bells that the earlier report of blackout is a misinformation by some online blogs.

     

    According to Ofulue, “It is not a blackout. Blackout don’t happen in the afternoon. The outage is between 8am – 6pm. In the evening power supply will be restored to customers between 6pm and 8am.”

     

    Olajide Kumapayi, chief technical officer of the electricity distribution company (DisCo), had announced that the project will begin on October 11.

    It’s 8-Week Outage, Not Blackout, Says Ikeja Electric

    The areas to be affected include Oregun, Police Training College, Oba Akran, Oke Ira, Ogba, Magodo, Anifowoshe and Omole Phase One.

     

    He noted that the outage became necessary because some of the 132Kv lines installed over 50 years ago had become obsolete and degraded due to time and usage.

     

    “The TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.

     

    “We will replace all the aluminium conductors with gap conductors which is more sophisticated to withstand heat and has more capacity to carry current.

     

    “The implication of this is that from 8am to 6pm every day, the substations controlling these areas will be switched off which will affect the feeders connected to them,” Kumapayi said.

     

    Also, Maximum Demand (MD) customers such as Ikeja City Mall, Police College, Lagos State University Teaching Hospital and the Ikeja High Court will be affected by the project.

     

    The chief technical officer disclosed that the TCN will also move to Alimosho and Agege axis in the next stage.

  • Ikeja Electric Announces 8-Week Blackout in Lagos

    Ikeja Electric Announces 8-Week Blackout in Lagos

     

    Ikeja Electric Plc on Monday announced an eight-week power outage in some areas in Lagos State.

     

    According to the Disco, this is to enable the Transmission Company of Nigeria (TCN) re-conduct its 132KV lines to boost electricity for Nigerians.

     

    Olajide Kumapayi, chief technical officer of the electricity distribution company (DisCo), said the project will begin on October 11.

     

    The areas to be affected include Oregun, Police Training College, Oba Akran, Oke Ira, Ogba, Magodo, Anifowoshe and Omole Phase One.

     

    He noted that the outage became necessary because some of the 132Kv lines installed over 50 years ago had become obsolete and degraded due to time and usage.

     

    “The TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.

     

    “We will replace all the aluminium conductors with gap conductors which is more sophisticated to withstand heat and has more capacity to carry current.

     

    “The implication of this is that from 8am to 6pm every day, the substations controlling these areas will be switched off which will affect the feeders connected to them,” Kumapayi said.

     

    Also, Maximum Demand (MD) customers such as Ikeja City Mall, Police College, Lagos State University Teaching Hospital and the Ikeja High Court will be affected by the project.

     

    The chief technical officer disclosed that the TCN will also move to Alimosho and Agege axis in the next stage.